Pennington Borough moves forward with road reconstruction projects

Date:

Share post:

Pennington Borough officials have unanimously adopted a $1.81 million bond ordinance to improve the conditions of Burd Street, Abey Drive and Kings Court.

During a Pennington Borough Council meeting, Council President Glen Griffiths, Councilman Charles Marciante, Councilwoman Elizabeth Semple, Councilwoman Catherine Chandler, Councilwoman Beverly Mills and Councilwoman Deborah Gnatt voted “yes” to approve the ordinance on May 6.

- Advertisement -

“The bond ordinance sounds huge, but what you do not see in that is the $1,038,900 in grants from the state Department of Transportation for municipal aid. So it is not like we are going out an immediately spending $1.8 million that we would have to raise the cap for,” said Mayor Joseph Lawver.

He said they bonded for $1.8 million because of the engineer’s projected estimate of the projects cost.

“We will try to scale it back to be closer to the total grant amount. We do not expect to spend the full $1.8 million,” Lawver said.

Reconstruction will take place to improve Abey Drive, Kings Court and Burd Street.

“When we do a road reconstruction project, it costs us two times as much as if we had caught the road with the base layer being intact and good. We have been taking a two pronged approach with the roads the past two years,” he said. “We have been working with the county and also using our municipal aid from the state DOT to address the roads that have gone to far and reconstruct them.”

Abey Drive and Kings Court are bonded for $1 million with $693,900 being covered by the state DOT grant. Burd Street is bonded for $793,500 with $345,00 in grant money set to cover some of the cost.

“To get these grants is critical. We could not afford to do these projects without that funding. We are grateful for every penny that we get. This is fantastic support that the state gives to us to maintain our infrastructure,” Lawver said. “We want to catch up on the worst roads and maintain the good roads in a cost efficient manner.”

The Burd Street reconstruction will be done during 2019 while Abey Drive and Kings Court work will begin at a later date, according to officials.

Stay Connected

1,226FansLike
1,976FollowersFollow

Current Issue

Latest News

Related articles

Tour des Arts

Courtesy of Hopewell Tour Des Arts Artist Guy Ciarca is a Hopewell Tour Des Arts participating artist. This year...

‘We are immensely grateful for their service’

The inaugural Mayor's Awards is honoring the heroic efforts of first responders across Hopewell Valley. The Mayor's Awards was...

Hopewell Valley Regional school district adopts 2024-25 budget with tax increase

Hopewell Valley residents will see tax increases after the Hopewell Valley Regional Board of Education's adoption of its...

Mercer County offers internship opportunities

Applications are now open for the 2024 Mercer County Student Internship Program. High school and college students who live, or attend school,...